The Perform Integrated Change Control process is conducted from project start through
completion and is the ultimate responsibility of the project manager.
Change requests can impact the project scope and the product scope,
as well as any project management plan component or any project document.
Changes may be requested by any stakeholder involved with
the project and may occur at any time throughout the project life cycle.
The applied level of change control is dependent upon the application area, complexity of the specific project,
contract requirements, and the context and environment in which the project is performed.