1- COST BASELINE
The cost baseline is the approved version of the time-phased project budget, excluding any management reserves,
which can only be changed through formal change control procedures.
-
2- PROJECT FUNDING REQUIREMENTS
Total funding requirements and periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline.
-
3- PROJECT DOCUMENTS UPDATES
Project documents that may be updated as a result of carrying out this process include but are not limited to:
-
* Cost estimates.
-
Cost estimates are updated to record any additional information.
-
* Project schedule.
-
Estimated costs for each activity may be recorded as part of the project schedule.
-
* Risk register.
-
New risks identified during this process are recorded in the risk register and managed using the risk management processes.