For smaller projects, defining activities, sequencing activities, estimating activity durations,
and developing the schedule model are so tightly linked that they are viewed as a single process that can
be performed by a person over a relatively short period of time. These processes are presented here
as distinct elements because the tools and techniques for each process are different.