1. *DEPENDENCY DETERMINATION AND INTEGRATION  

Dependencies may be characterized by the following attributes:

mandatory or discretionary, internal or external (as described below):  

  • *Mandatory dependencies. 

  • Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work.  

  • *Discretionary dependencies.

  •  Discretionary dependencies are sometimes referred to as preferred logic, preferential logic, or soft logic.  

  • *External dependencies. 

  • External dependencies involve a relationship between project activities and non-project activities.  

  • *Internal dependencies.

  •  Internal dependencies involve a precedence relationship between project activities and are generally inside the project team's control.  

  1. *LEADS AND LAGS  

A lead is the amount of time a successor activity can be advanced with respect to a predecessor activity.

For example, on a project to construct a new office building, the landscaping could be scheduled to start 2 weeks prior to the scheduled punch list completion.

This would be shown as a finish-to-start with a 2-week lead as shown in Figure 6.10. Lead is often represented as a negative value for lag in scheduling software. 

A lag is the amount of time a successor activity will be delayed with respect to a predecessor activity.

For example, a technical writing team may begin editing the draft of a large document 15 days after they begin writing it.

This can be shown as a start-to-start relationship with a 15-day lag as shown in Figure 6.10.

Lag can also be represented in project schedule network diagrams as shown in Figure 6.11

in the relationship between activities H and I (as indicated by the nomenclature SS+10

(start-to-start plus 10 days lag) even though the offset is not shown relative to a timescale).